Project details

Technical overview of the SS Energy solar plant — commissioned and operational.

HPSEBL Grid ConnectedPPA ActiveCommissioned 2022Telemetry Monitored

Capacity & Output

1MW installed capacity. Peak generation of 6,500 units per day. Grid-connected via 33kV line to HPSEBL substation.

Capacity & Output

HPSEBL PPA

Long-term Power Purchase Agreement with Himachal Pradesh State Electricity Board. Tariff and tenure as per state policy for renewable projects.

HPSEBL PPA

Telemetry & Monitoring

Remote monitoring system installed. Real-time generation data, fault detection, and performance analytics accessible to the operations team.

Telemetry & Monitoring

Land & Location

27 Bigha in Chobin Village, Baijnath, Kangra. Favorable solar irradiance, accessible road, and proximity to grid infrastructure.

Land & Location

Expansion Roadmap

Phase 2 planned to take total capacity to 2.20MW. Land and grid feasibility already assessed. Looking for the right partner to execute.

Expansion Roadmap

Ready to talk numbers?

Serious investors, developers, and institutions — we respond directly and fast.

Discuss this project